Skanska has received a $275 million award from an existing, unnamed client to build a new 48-megawatt data center in Georgia, the Swedish construction company said in a press release dated Nov. 26, 2026. The contract, worth about SEK 2.8 billion, will be booked in Skanska’s U.S. order intake for the fourth quarter of 2026.
It is at least the fourth Georgia data center contract Skanska has announced in 2026, and it comes as data center work keeps carrying a construction sector that is otherwise slowing. The Federal Reserve’s latest Beige Book, covered by RealtyWire on Nov. 26, described housing weakening under mortgage rates near 7% while data centers supported construction activity.
What the Georgia data center contract covers
According to Skanska, the project involves a new 48MW facility totaling 244,730 square feet, or about 22,700 square meters. The scope covers the building shell and interior fit-out for technical spaces, support areas and office functions. Skanska will also build an 860-square-foot ancillary water treatment building on the site.
Construction began in November 2026 and is expected to be completed in October 2028, the company said. The release does not name the client, the county or city where the facility is being built, or the end user of the data center.
Skanska described the deal as an “additional award” with an existing client, the same language it has used for a series of follow-on contracts in the state this year.
A pattern of staged awards in Georgia
Skanska’s 2026 Georgia announcements show a recurring structure: a smaller initial contract followed months later by a much larger supplemental one for a building of the same size.
- April 9: A $75 million contract for a 22,700-square-meter data center with site work, underground utilities, an administration space and five data halls. Construction began in March 2026, with completion set for the first quarter of 2028.
- June 23: A $255 million supplemental contract for a 22,700-square-meter data center with the same scope, the same March 2026 start and the same first-quarter 2028 completion.
- Sept. 22: An $84 million contract to begin work on a roughly 22,700-square-meter (244,730-square-foot) data center with five colocation data halls designed for 48MW, with work starting in November 2026.
The specifications in the new award, 48MW and 244,730 square feet with construction starting in November 2026, match those of the September contract. On our reading, the $275 million award most likely extends that earlier job, which would bring the project to about $359 million in announced Skanska contracts. Skanska’s Nov. 26 release does not say whether the two awards cover the same facility, and the September release gave a third-quarter 2028 completion date rather than the October 2028 date now cited. The April and June contracts likewise describe matching buildings, suggesting a two-stage award of about $330 million.
Skanska has not said whether the same client stands behind all of its Georgia work.
Part of a larger data center book
The Georgia award adds to a string of U.S. data center contracts for Skanska in 2026. In August, the company announced a $238 million contract for a second data center building in Virginia and, a week later, a $1.2 billion contract to build four data centers in the Southeast totaling about 808,000 square feet, with construction scheduled from the third quarter of 2026 to the third quarter of 2028.
Georgia has drawn a string of large data center proposals, including a 1.25-gigawatt campus filed in Lovejoy, Ga., south of Atlanta. Contractor surveys point the same way: about one in six contractors reported data center work in a recent construction backlog survey. RealtyWire’s coverage of technology and data center real estate has tracked that shift through 2026.
The staged pattern matters for anyone tracking data center construction spending. Based on Skanska’s own releases this year, the first contract announced for a Georgia facility has been less than a third of the total later disclosed for a building of the same size. Headline figures from initial awards can understate a project’s eventual value.
The new contract runs for nearly two years. If Skanska keeps to its schedule, the 48MW facility will be finished in October 2028.